TIMELINE 1.84 KB
Newer Older
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79

Milestone		Sept	Oct	Nov	Dec	Jan	Feb	Mar	Apr	May	Jun	Jul	Aug
_________________________________________________________________________________________________________________________

gstlal-inspiral
 CODE RELEASE
  SCHEDULE
++++++++++++++++++++++

Stabilize		|-------|
code for "offline"
analysis useful for 
e.g. MDCS

Prepare offline			|---|
inspiral analysis 
release candidate

Stabilize online                    |------|
inspiral
code for release

Prepare online				   |--|
code release
as a point release
for gstlal-inspiral


Milestone		Sept	Oct	Nov	Dec	Jan	Feb	Mar	Apr	May	Jun	Jul	Aug
_________________________________________________________________________________________________________________________

REVIEW SCHEDULE
++++++++++++++++++++++

Face-to-face meeting
at Caltech						  |---|


Milestone		Sept	Oct	Nov	Dec	Jan	Feb	Mar	Apr	May	Jun	Jul	Aug
_________________________________________________________________________________________________________________________

CBC MDC SCHEDULE
++++++++++++++++++++++

BNS spin MDC offline	|---------------------|
preliminary

BNS spin MDC offline			      |--->
with release

NSBH spin MDC offline	|---------------------|
preliminary

NSBH spin MDC offline			      |--->
with release

BBH spin MDC offline	|---------------------|
preliminary

BBH spin MDC offline			      |--->
with release

S6 Replay MDC with
ER5 online code			|--------|

S6 Replay MDC			    |--------|
with prototype
ER6 code

S6 Replay tests					|-------|
with ER6 code

S6 Replay final
version							|-------->


Milestone		Sept	Oct	Nov	Dec	Jan	Feb	Mar	Apr	May	Jun	Jul	Aug
_________________________________________________________________________________________________________________________

gstlalcbc's avatar
gstlalcbc committed
80
ENGINEERING RUNS
81 82 83 84 85 86 87
++++++++++++++++++++++

ER6						|-------|


* |---> Denotes timelines tied to decisions by a broader working group (e.g. CBC) or review team.